Geothermal Well Updates



5.25.11 :: 2:32 pm
The geothermal test well is going along smoothly. We have passed the halfway mark and expect to be completed next week. The well is a little deeper now than the Prudential building is high [749 feet]. The well will be 1,500 feet deep upon completion.

Thanks to all for your patience. So far, the noise and vibration has been much less than anticipated.


5.26.11 :: 9:57 am

We are now 2/3 the way down. 900 feet with 600 to go!

5.27.11 :: 9:00 am

We are at 1,340 feet. Looks like we may finish today and pack up the rig on Tuesday.